| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20100926 | Name of Scheme: AGOUS GRAMM PANCHAYAT WATER SUPPLY SCHEME | No. of Villages: 1 | No. of Habitation Covered: 7 |
| Total Population Covered: 7444 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 14-Nov-2024 | Actual Date of Completion (Capex): 16-Apr-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 35.00/233.81 | AGOUS ZONE-2 | 26.949333 | 79.722428 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE PUMP | 1100/60 | AGOUS ZONE-2 | 26.949333 | 79.722428 |
| 2 | SUBMERSIBLE PUMP | 500/56 | AGOUS ZONE-1 | 26.949333 | 79.722428 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT 1 | 325/18 | AGOUS ZONE-2 | 26.949333 | 79.722428 |
| 2 | OHT-2 | 150/14 | AGOUS ZONE-1 | 26.949333 | 79.722428 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 80 | 0.002 | RISING MAINS |
| 2 | DI | 100 | 0.043 | RISING MAINS |
| 3 | DI | 150 | 0.0285 | RISING MAINS |
| 4 | DI | 200 | 0.0058 | RISING MAINS |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 90 | 3.036 | DISTRIBUTION |
| 2 | HDPE | 63 | 7.327 | DISTRIBUTION |
| 3 | HDPE | 110 | 2.66 | DISTRIBUTION |
| 4 | HDPE | 140 | 1.148 | DISTRIBUTION |
| 5 | HDPE | 160 | 0.306 | DISTRIBUTION |
| 6 | HDPE | 180 | 0.552 | DISTRIBUTION |
| 7 | HDPE | 200 | 0.757 | DISTRIBUTION |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 1412 |