Project Completion Certificate (Ground Water)
Scheme ID: 20101556 Name of Scheme: Ronwa Besunpur Rural Water Supply Scheme No. of Villages: 3 No. of Habitation Covered: 5
Total Population Covered: 4423 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 09-May-2024 Actual Date of Completion (Capex): 31-Oct-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 24/168.79 Rowa Bishunpur 25.99817 83.04467
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 650/46 Rowa Bishunpur 25.99817 83.04467
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 200/12 Rowa Bishunpur 25.99817 83.04467
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 K-7/DI PIPE 125 0.04
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 63 11.481
2 HDPE Pipe PN-6: Class PE-100 75 0.774
3 HDPE Pipe PN-6: Class PE-100 90 1.275
4 HDPE Pipe PN-6: Class PE-100 110 0.675
5 HDPE Pipe PN-6: Class PE-100 140 0.463
HSC Connection
Sno. Total Nos.
1 505
Other Details
2.30
2.30
2.30
03-Feb-2025
04-Feb-2025