| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20101559 | Name of Scheme: KARENDUA GRAM PANCHAYAT RURAL WATER SUPPLY SCHEME | No. of Villages: 3 | No. of Habitation Covered: 13 |
| Total Population Covered: 4859 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 21-Mar-2023 | Actual Date of Completion (Capex): 29-Oct-2023 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 30.39/189.73 | KARANUWA | 26.10742 | 83.16786 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE PUMP | 700/45 | KARANUWA | 26.10742 | 83.16786 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 150/12 | KARANUWA | 26.10742 | 83.16786 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | K-7/DI PIPE | 125 | 0.03 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE Pipe PN-6: Class PE-100 | 63 | 13.642 | |
| 2 | HDPE Pipe PN-6: Class PE-100 | 75 | 0.729 | |
| 3 | HDPE Pipe PN-6: Class PE-100 | 90 | 0.119 | |
| 4 | HDPE Pipe PN-6: Class PE-100 | 140 | 0.017 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 481 |