Project Completion Certificate (Ground Water)
Scheme ID: 20101559 Name of Scheme: KARENDUA GRAM PANCHAYAT RURAL WATER SUPPLY SCHEME No. of Villages: 3 No. of Habitation Covered: 13
Total Population Covered: 4859 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 21-Mar-2023 Actual Date of Completion (Capex): 29-Oct-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 30.39/189.73 KARANUWA 26.10742 83.16786
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 700/45 KARANUWA 26.10742 83.16786
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 150/12 KARANUWA 26.10742 83.16786
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 K-7/DI PIPE 125 0.03
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 63 13.642
2 HDPE Pipe PN-6: Class PE-100 75 0.729
3 HDPE Pipe PN-6: Class PE-100 90 0.119
4 HDPE Pipe PN-6: Class PE-100 140 0.017
HSC Connection
Sno. Total Nos.
1 481
Other Details
3.34
3.34
3.34
31-Jan-2024
01-Feb-2024