| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20101579 | Name of Scheme: BIBIPUR WATER SUPPLY SCHEME | No. of Villages: 3 | No. of Habitation Covered: 7 |
| Total Population Covered: 2946 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 10-Aug-2023 | Actual Date of Completion (Capex): 05-Jan-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 23.5/82.33 | Bibipur | 26.13732 | 83.08937 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible Pump | 400/49 | Bibipur | 26.13732 | 83.08937 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 125/16 | Bibipur | 26.13732 | 83.08937 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | K-7/DI PIPE | 200 | 0.05 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE Pipe PN-6: Class PE-100 | 63 | 9.025 | |
| 2 | HDPE Pipe PN-6: Class PE-100 | 75 | 0.149 | |
| 3 | HDPE Pipe PN-6: Class PE-100 | 140 | 0.289 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 447 |