Project Completion Certificate (Ground Water)
Scheme ID: 20101586 Name of Scheme: Nawapura water supply scheme No. of Villages: 2 No. of Habitation Covered: 6
Total Population Covered: 2758 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 04-Aug-2024 Actual Date of Completion (Capex): 20-Jul-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 15/97.96 Nawapura 26.127953 83.086875
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 400/45 Nawapura 26.127953 83.086875
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 150/12 Nawapura 26.127953 83.086875
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 K-7/DI PIPE 150 0.05
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 63 11.580
2 HDPE Pipe PN-6: Class PE-100 75 0.400
3 HDPE Pipe PN-6: Class PE-100 90 0.160
4 HDPE Pipe PN-6: Class PE-100 110 1.700
HSC Connection
Sno. Total Nos.
1 351
Other Details
1.93
1.93
1.60
23-Oct-2024
24-Oct-2024