Project Completion Certificate (Ground Water)
Scheme ID: 20101949 Name of Scheme: GHORHA WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 11
Total Population Covered: 1863 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 13-Mar-2024 Actual Date of Completion (Capex): 18-Jun-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 17/58.06 GHORHA 26.106800 81.754074
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE 400 LPM / 54 M GHORHA 26.106800 81.754074
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 125/16 GHORHA 26.106800 81.754074
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-7 100 0.025
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 5.903
2 HDPE 90 1.381
3 HDPE 110 1.229
4 HDPE 140 1.172
5 HDPE 160 0.236
HSC Connection
Sno. Total Nos.
1 297
Other Details
1.94
0.00
1.92
18-Sep-2024
21-Dec-2024