| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20102064 | Name of Scheme: MURADGAM PUR PURSI VILLAGE WATER SUPPLY SCHEME | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 9763 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 31-May-2023 | Actual Date of Completion (Capex): 01-Nov-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 30m/63m | Muradgram Pursi | 28.740986 | 77.513388 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 1350/53 | Muradgram Pursi | 28.740986 | 77.513388 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 400/14 | Muradgram Pursi | 28.740986 | 77.513388 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | D.I | 200 | .010 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 6.624 | |
| 2 | HDPE | 75 | .463 | |
| 3 | HDPE | 90 | .439 | |
| 4 | HDPE | 110 | .841 | |
| 5 | HDPE | 125 | .699 | |
| 6 | HDPE | 140 | .402 | |
| 7 | HDPE | 160 | .553 | |
| 8 | HDPE | 180 | .093 | |
| 9 | HDPE | 200 | .105 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 1165 |