Project Completion Certificate (Ground Water)
Scheme ID: 20102367 Name of Scheme: NAGALA CHITI VILLAGE WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 665 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 07-Feb-2024 Actual Date of Completion (Capex): 01-Oct-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 19M/81.60M NAGLA CHITTI 28.424853 77.660818
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-01 50KL/12M NAGLA CHITTI 28.424853 77.660818
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE 80 0.080
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 3.718
2 HDPE 75 0.491
3 HDPE 110 0.171
HSC Connection
Sno. Total Nos.
1 156
Other Details
1.15
1.19
1.19
01-Jul-2024
01-Oct-2024