| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20106718 | Name of Scheme: ANDMAU GRAM PANCHAYAT WATER SUPPLY SCHEME | No. of Villages: 1 | No. of Habitation Covered: 2 |
| Total Population Covered: 1750 | Base Year: 2023 | Intermediate Year: 2033 | Design Year: 2053 |
| Date of Completion (As per Contract): 25-Sep-2024 | Actual Date of Completion (Capex): 30-Jun-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBE WELLS | 18/93.35 | ANDMAU | 25".62970935 N | 81.15070988',E |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | submersible | 360 / 55 | ANDMAU | 25.62970935 N | 81.15070988"8 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT.1 | 125KL / 12M | ANDMAU | 25",62970935 N | 81.15070988',E |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | D.t. K-9 | 80 | 0.01326 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 200 | 0.5424 | |
| 2 | HDPE | 180 | 0.188 | |
| 3 | HDPE | 160 | 0.1715 | |
| 4 | HDPE | 125 | 0.379 | |
| 5 | HDPE | 110 | 0.2168 | |
| 6 | HDPE | 90 | 0.535 | |
| 7 | HDPE | 75 | 1.0548 | |
| 8 | HDPE | 140 | 1.124 | |
| 9 | HDPE | 63 | 1.5803 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 335 |