| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 8359404 | Name of Scheme: Bikhra | No. of Villages: 1 | No. of Habitation Covered: 4 |
| Total Population Covered: 2400 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 14-Sep-2022 | Actual Date of Completion (Capex): 15-Jun-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 20.0M / 62.5 M | Bikhra | 26.783154 | 79.5111111 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | (36.2 M3/Hr.) / 46 M | Bikhra | 26.783154 | 79.5111111 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 150 KL / 16 M | Bikhra | 26.788554 | 79.511112 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | D.I. | 100 | 0.016 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 4.981 | |
| 2 | HDPE | 75 | 0.568 | |
| 3 | HDPE | 90 | 0.730 | |
| 4 | HDPE | 110 | 0.364 | |
| 5 | HDPE | 140 | 0.082 | |
| 6 | HDPE | 160 | 0.173 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 515 |