Project Completion Certificate (Ground Water)
Scheme ID: 8359424 Name of Scheme: Etaili No. of Villages: 1 No. of Habitation Covered: 17
Total Population Covered: 4370 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 12-Sep-2022 Actual Date of Completion (Capex): 10-Nov-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 27.06 M / 120.86 M Etaili 26.7574779* 79.36231971*
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible (57.9 M3/Hr.) / 40 M Etaili 26.7574779* 79.36231971*
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 300 Kl / 12 M Etaili 26.75756212* 79.36211742*
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I. 150 0.017
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 12.168
2 HDPE 75 4.913
3 HDPE 90 1.624
4 HDPE 110 1.048
5 HDPE 140 0.667
6 HDPE 160 0.298
7 HDPE 180 0.145
HSC Connection
Sno. Total Nos.
1 623
Other Details
3.76
2.96
2.96
28-Feb-2024
01-Mar-2024