Project Completion Certificate (Ground Water)
Scheme ID: 8360529 Name of Scheme: Paraspur GP WSS No. of Villages: 1 No. of Habitation Covered: 3
Total Population Covered: 2115 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 31-Dec-2025 Actual Date of Completion (Capex): 02-Apr-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 500LPM 164.30 PARASPUR 27.372416 83.147227
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBILE 500/41 PARASPUR 27.372416 83.147227
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 150/12M PARASPUR 27.243609 83.147001
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI/K9 100 33.33
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 PE 100 PN6 /HDPE 63 2521.50
2 PE 100 PN6 /HDPE 75 488
3 PE 100 PN6 /HDPE 90 304
4 PE 100 PN6 /HDPE 110 992
5 PE 100 PN6 /HDPE 125 122
HSC Connection
Sno. Total Nos.
1 333
Other Details
1.51
1.48
1.48
15-Jan-2025
12-Apr-2025