Project Completion Certificate (Ground Water)
Scheme ID: 8360550 Name of Scheme: SATHIPAR WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 1490 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 27-Feb-2023 Actual Date of Completion (Capex): 03-Feb-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 36.15/113.69 Sathipar 26.7260 83.2930
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 24/39 Sathipar 26.7260 83.2930
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Overhead Tank-1 75/12 Sathipar 26.7260 83.2930
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 100 0.03 Laying Completed
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 9.652 Laying Completed
2 HDPE 75 1.402 Laying Completed
3 HDPE 110 1.501 Laying Completed
HSC Connection
Sno. Total Nos.
1 489
Other Details
1.91
0.00
1.91
05-May-2025
19-Apr-2025