Project Completion Certificate (Ground Water)
Scheme ID: 8360682 Name of Scheme: MANDAURA VILLAGE WATER SCHEME No. of Villages: 3 No. of Habitation Covered: 3
Total Population Covered: 3411 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 26-Jul-2023 Actual Date of Completion (Capex): 11-Dec-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 19.31 MTR / 139.73 MTR MANDAURA 29.176417 73.399529
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 700 LPM / 40 MTR MANDAURA 29.176417 73.399529
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 200 KL / 14 MTR MANDAURA 29.176378 78.399753
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 K-7 DI PIPE 150 0.015
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE PN -6 CLASS PE-100 125 1.166
2 HDPE PIPE PN -6 CLASS PE-100 110 1.107
3 HDPE PIPE PN -6 CLASS PE-100 90 0.585
4 HDPE PIPE PN -6 CLASS PE-100 75 1.151
5 HDPE PIPE PN -6 CLASS PE-100 63 6.006
HSC Connection
Sno. Total Nos.
1 577
Other Details
2.40
0.00
2.40
09-Jun-2024
10-Jun-2024