Project Completion Certificate (Ground Water)
Scheme ID: 8360855 Name of Scheme: JIGINIA MIYAON WATER SUPPLY SCHEME No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 2780 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 11-Feb-2023 Actual Date of Completion (Capex): 29-Jan-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 160m Jigniya Miyaon 26.56812 83.316204
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submercible 650LPM/ 41m Jigniya Miyaon 26.56812 83.316204
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 ESR 175KL/ 12m Jigniya Miyaon 26.56812 83.316204
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI Pipe 150 0.035
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 9.993
2 HDPE 75 0.218
3 HDPE 90 0.223
4 HDPE 110 0.195
5 HDPE 140 0.135
6 HDPE 160 0.482
7 HDPE 180 0.178
HSC Connection
Sno. Total Nos.
Other Details
2.84
0.00
2.75
29-Apr-2023
19-Nov-2024