| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 8361028 | Name of Scheme: Azizullah Urf Chakia, Water Supply Scheme | No. of Villages: 3 | No. of Habitation Covered: 5 |
| Total Population Covered: 3100 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 11-May-2023 | Actual Date of Completion (Capex): 24-Oct-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 21.03/174.69 | Azizullah Urf Chakia | 26.837023 | 83.298021 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible Pump | 42/41 | Azizullah Urf Chakia | 26.837023 | 83.298021 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | Over Head Tank-1 | 175/14 | Azizullah Urf Chakia | 26.836861 | 83.29829 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 150 | 0.035 | Completed |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 8.5349 | Completed |
| 2 | HDPE | 75 | 1.993 | Completed |
| 3 | HDPE | 90 | 0.579 | Completed |
| 4 | HDPE | 110 | 0.436 | Completed |
| 5 | HDPE | 160 | 0.462 | Completed |
| 6 | HDPE | 200 | 0.850 | Completed |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 345 |