Project Completion Certificate (Ground Water)
Scheme ID: 8361028 Name of Scheme: Azizullah Urf Chakia, Water Supply Scheme No. of Villages: 3 No. of Habitation Covered: 5
Total Population Covered: 3100 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 11-May-2023 Actual Date of Completion (Capex): 24-Oct-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 21.03/174.69 Azizullah Urf Chakia 26.837023 83.298021
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 42/41 Azizullah Urf Chakia 26.837023 83.298021
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Over Head Tank-1 175/14 Azizullah Urf Chakia 26.836861 83.29829
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 0.035 Completed
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 8.5349 Completed
2 HDPE 75 1.993 Completed
3 HDPE 90 0.579 Completed
4 HDPE 110 0.436 Completed
5 HDPE 160 0.462 Completed
6 HDPE 200 0.850 Completed
HSC Connection
Sno. Total Nos.
1 345
Other Details
2.41
0.00
2.67
23-Oct-2024
06-May-2025