Project Completion Certificate (Ground Water)
Scheme ID: 8361578 Name of Scheme: SIDIPUR VILLAGE WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 4770 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 20-Mar-2023 Actual Date of Completion (Capex): 31-Mar-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 24/97 SIDIPUR 28.620038 77.592487
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 600/48 SIDIPUR 28.620038 77.592487
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 150/12 SIDIPUR 28.620038 77.592487
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I 100 0.019
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 3.627
2 HDPE 75 1.472
3 HDPE 90 0.397
4 HDPE 110 0.521
5 HDPE 140 0.037
6 HDPE 160 0.283
HSC Connection
Sno. Total Nos.
1 499
Other Details
1.86
1.89
1.89
31-Oct-2024
01-Nov-2024