| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 8361975 | Name of Scheme: KAMHARI | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 1581 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 30-Apr-2025 | Actual Date of Completion (Capex): 20-Oct-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | 200mmX150mm | 29.90m/140.91m | Kamhari | 25.325331 | 83.291992 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible Borewell Pump | 18.89(CUM)/55mtr | Kamhari | 25.325331 | 83.291992 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OVERHEAD TANK | 100KL/12M | Kamhari | 25.325391 | 83.292019 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI-K9 | 80 | 0.076 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 3.951 | |
| 2 | HDPE | 75 | 0.406 | |
| 3 | HDPE | 90 | 0.064 | |
| 4 | HDPE | 110 | 0.028 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 277 |