| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 8362937 | Name of Scheme: BARUHA | No. of Villages: 1 | No. of Habitation Covered: 4 |
| Total Population Covered: 2082 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 30-Jun-2025 | Actual Date of Completion (Capex): 26-Jun-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell 600LPM | 24.12 m/116.03m | Baruha | 25.746046 | 80.782654 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Sumersible 15HP | 600LPM/60M | Baruha | 25.746046 | 80.782654 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 150KL/16M | Baruha | 25.746046 | 80.782654 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI K-9 | 125 | 0.03 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE Pipe | 63 | 7.0653 | |
| 2 | HDPE Pipe | 75 | 0.8756 | |
| 3 | HDPE Pipe | 90 | 0.0234 | |
| 4 | HDPE Pipe | 110 | 1.5841 | |
| 5 | HDPE Pipe | 160 | 0.953 | |
| 6 | HDPE Pipe | 180 | 0.839 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 415 |