Project Completion Certificate (Ground Water)
Scheme ID: 8386596 Name of Scheme: Khar Khuta No. of Villages: 1 No. of Habitation Covered: 2
Total Population Covered: 2970 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 27-May-2023 Actual Date of Completion (Capex): 06-Dec-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 22.17/112.79 Khar Khuta 26.5645 83.4658
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 42/41 Khar Khuta 26.5645 83.4658
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Overhead Tank-1 150/14 Khar Khuta 26.5645 83.4658
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 0.015 Laying Completed
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 7.251 Laying Completed
2 HDPE 75 0.132 Laying Completed
3 HDPE 110 1.001 Laying Completed
4 HDPE 140 0.132 Laying Completed
HSC Connection
Sno. Total Nos.
1 600
Other Details
2.04
0.00
2.04
05-Dec-2024
06-May-2025