| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 8386636 | Name of Scheme: POCHHIYA BRAHM ASTHAN Water Supply Scheme | No. of Villages: 1 | No. of Habitation Covered: 7 |
| Total Population Covered: 3370 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 27-May-2023 | Actual Date of Completion (Capex): 06-Jan-2023 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 24.13/138.74 | Pochhiya Brahm Asthan | 26.6419 | 83.4551 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible Pump | 48/41 | Pochhiya Brahm Asthan | 26.6419 | 83.4551 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | Over Head Tank- | 150/14 | Pochhiya Brahm Asthan | 26.6425 | 83.4558 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 150 | 0.028 | Completed |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 9.039 | Completed |
| 2 | HDPE | 75 | 0.337 | Completed |
| 3 | HDPE | 90 | 0.489 | Completed |
| 4 | HDPE | 110 | 0.820 | Completed |
| 5 | HDPE | 140 | 1.172 | Completed |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |