| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 8386656 | Name of Scheme: SAREHUAKALA | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 1461 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 28-Feb-2023 | Actual Date of Completion (Capex): 23-Dec-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | 200mmX150mm | 26.94m/143.27m | Sarehukala | 25.341873 | 83.216868 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible Pump | 19.04(CUM/55(mtr.) | Sarehukala | 25.341873 | 83.216868 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OVERHEAD TANK | 100KL/12M | Sarehukala | 25.341926 | 83.216805 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI-K9 | 80 | 0.076 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 4.74 | |
| 2 | HDPE | 90 | 0.230 | |
| 3 | HDPE | 110 | 0.992 | |
| 4 | HDPE | 140 | 0.015 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 232 |