Project Completion Certificate (Ground Water)
Scheme ID: 8388519 Name of Scheme: Dohri No. of Villages: 3 No. of Habitation Covered: 4
Total Population Covered: 2008 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 05-Mar-2023 Actual Date of Completion (Capex): 30-Jun-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 23(m) / 317.8(m) Dohri 26.175153 81.259995
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 600(M³) / 45(Mtr.) Dohri 26.175153 81.259995
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Elevated Storage Reservoir 150 (KL) / 16(Mtr.) Dohri 26.175153 81.259995
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI-K9 150 0.012
2 DI-K9 100 0.007
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 5.320
2 HDPE 75 4.297
3 HDPE 90 1.002
4 HDPE 110 0.075
5 HDPE 125 1.488
6 HDPE 160 0.057
HSC Connection
Sno. Total Nos.
1 390
Other Details
2.26
0.00
2.30
27-May-2025
10-Jun-2025