Project Completion Certificate (Ground Water)
Scheme ID: 8388598 Name of Scheme: KAKU MAU No. of Villages: 1 No. of Habitation Covered: 3
Total Population Covered: 3150 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 05-Mar-2023 Actual Date of Completion (Capex): 25-Dec-2022
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewells 24.07 Mtr/ 118.84 Mtr KAKU MAU 27.266604 80.318558
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 0.7 M³ per Min /45Mtr KAKU MAU 27.266604 80.318558
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 200 KL/ 16 Mtr KAKU MAU 27.366455 80.318611
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I. Pipe 150 0.0224
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6, Class PE-100 63 1.986
2 HDPE Pipe PN-6, Class PE-100 75 3.624
3 HDPE Pipe PN-6, Class PE-100 90 0.323
4 HDPE Pipe PN-6, Class PE-100 110 1.224
5 HDPE Pipe PN-6, Class PE-100 125 0.060
6 HDPE Pipe PN-6, Class PE-100 140 1.351
7 HDPE Pipe PN-6, Class PE-100 160 0.771
HSC Connection
Sno. Total Nos.
1 392
Other Details
3.31
0.00
2.39
24-Mar-2023
25-Dec-2024