Project Completion Certificate (Ground Water)
Scheme ID: 8388602 Name of Scheme: KATKA No. of Villages: 1 No. of Habitation Covered: 4
Total Population Covered: 2667 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 05-Mar-2023 Actual Date of Completion (Capex): 29-Apr-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewells 24 Mtr/ 102 Mtr KATKA 27.348427 80.316729
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 0.6 M³ per Min /45 Mtr KATKA 27.348427 80.316729
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 175 KL/ 14 Mtr KATKA 27.348271 80.316583
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I. Pipe 150 0.01977
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6, Class PE-100 63 2.918
2 HDPE Pipe PN-6, Class PE-100 75 1.664
3 HDPE Pipe PN-6, Class PE-100 90 1.040
4 HDPE Pipe PN-6, Class PE-100 110 0.062
5 HDPE Pipe PN-6, Class PE-100 125 0.553
6 HDPE Pipe PN-6, Class PE-100 140 0.785
7 HDPE Pipe PN-6, Class PE-100 160 0.585
HSC Connection
Sno. Total Nos.
1 299
Other Details
2.48
0.00
2.09
28-Jul-2023
24-Dec-2024