Project Completion Certificate (Ground Water)
Scheme ID: 8388891 Name of Scheme: GRAM PANCHAYAT PURAINA ABDUL RAHMANPUR PURAINA ABDUL RAHMANPUR VILLAGE WATER SCHEME No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 4686 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 22-Sep-2023 Actual Date of Completion (Capex): 13-Mar-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewells 18.11 MTR /127.90 MTR PURAINA ABDULPUR RAHAMAN 78.366422 78.366422
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE 700 LMP/40MTR PURAINA ABDULPUR RAHAMAN 78.366422 78.366422
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 175 KL /14 MTR PURAINA ABDULPUR RAHAMAN 78.366422 78.366422
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 K-7 DI PIPE 150 0.030
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE PN-6 CLASS PE-100 110 0.322
2 HDPE PIPE PN-6 CLASS PE-100 90 0.506
3 HDPE PIPE PN-6 CLASS PE-100 75 0.500
4 HDPE PIPE PN-6 CLASS PE-100 63 5.795
5 HDPE PIPE PN-6 CLASS PE-100 125 0.065
6 HDPE PIPE PN-6 CLASS PE-100 125 0.065
7 HDPE PIPE PN-6 CLASS PE-100 180 0.022
HSC Connection
Sno. Total Nos.
1 498
Other Details
2.12
2.09
2.12
12-Sep-2025
13-Sep-2025