Project Completion Certificate (Ground Water)
Scheme ID: 8389108 Name of Scheme: PIDHWAL No. of Villages: 1 No. of Habitation Covered: 10
Total Population Covered: 4349 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 20-Sep-2023 Actual Date of Completion (Capex): 11-Sep-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Strainer (m) 32.54 TW 26.083556 83.574012
2 Plain Pipe (m) 175.65 TW 26.083556 83.574012
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 1000/45 TW 26.083556 83.574012
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 RCC 225/13 OHT 26.083556 83.574012
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI k7 150 0.03
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PN6 PE 100 63 13.45
2 HDPE PN6 PE 100 75 1.53
3 HDPE PN6 PE 100 90 2.1
4 HDPE PN6 PE 100 110 1.2
5 HDPE PN6 PE 100 140 0.33
6 HDPE PN6 PE 100 200 0.15
HSC Connection
Sno. Total Nos.
1 603
Other Details
3.68
3.68
0.00
10-Sep-2024
11-Sep-2024