| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 8389917 | Name of Scheme: SAFAURA | No. of Villages: 2 | No. of Habitation Covered: 2 |
| Total Population Covered: 1840 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 15-Apr-2023 | Actual Date of Completion (Capex): 23-Nov-2023 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell Work | 12.03/88.06 | Safaura | 28°14'41.1"N | 79°48'17.0"E |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible Pump 7.5 HP | .39/34 | Safaura | 28°14'41.1"N | 79°48'17.0"E |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | Over Head Tank (Conventional) | 150/10 | Safaura | 28°14'41.5"N | 79°48'16.5"E |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI Rising main K-7 | 125 | .036 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE Pipe | 63 | 3.041 | |
| 2 | HDPE Pipe | 75 | .153 | |
| 3 | HDPE Pipe | 90 | .136 | |
| 4 | HDPE Pipe | 125 | .137 | |
| 5 | HDPE Pipe | 140 | 0.074 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 344 |