Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in
Check List Form

JAKSON - VISHVARAJ (JV)
[JAKSON] (Basti)

Project Completion Plan


Minutes of Meeting Date - 01-Jul-2025

Jackson Vishvaraj JV has integrated 19 schemes on JJM Portal against 01 HGJ Certified Schemes. 02 schemes are functional and 16 schemes are non-functional due network issue. Firm has assured to make all 16 remaining schemes functional by 31.07.25. Software troubleshooting is going on.


Minutes of Meeting Date - 22-Jul-2025

Jackson Vishvaraj JV has integrated 19 schemes on JJM Portal against 01 HGJ Certified Schemes. 03 schemes are functional and 16 schemes are non-functional due network issue. Firm has assured to make all 16 remaining schemes functional by 31.07.25. Software troubleshooting is going. 01 Schemes will be integrated by 31.07.25


Minutes of Meeting Date - 29-Jul-2025

Jackson Vishvaraj JV has integrated 19 schemes on JJM Portal against 01 HGJ Certified Schemes. 05 schemes are functional and 14 schemes are non-functional due to weather & network issue. Firm has assured to make 07 more schemes functional by 08.08.25. In some schemes displayed data is fluctuating & calibration of analyzer is required, their team is working on it.


Minutes of Meeting Date - 05-Aug-2025

Jackson Vishvaraj JV has integrated 30 schemes on JJM Portal against 01 HGJ Certified Schemes. 06 schemes are functional and other remaining schemes are non-functional due to bad weather & network issue. Firm has assured to make 05 more schemes functional by 15.08.25. In some schemes displayed data is fluctuating & calibration of analyzer is required, their team is working on it.


Minutes of Meeting Date - 12-Aug-2025

Jackson Vishvaraj JV has integrated 31 schemes on JJM Portal against 01 HGJ Certified Schemes. 04 schemes are functional and other remaining schemes are non-functional due to bad weather & network issue. Firm has assured to make 05 more schemes functional by 22.08.25. In some schemes displayed data is fluctuating & calibration of analyzer is required, their team is working on it.


Minutes of Meeting Date - 19-Aug-2025

Jackson Vishvaraj JV has integrated 32 schemes on JJM Portal against 01 HGJ Certified Schemes. 06 schemes are functional and other remaining schemes are non-functional due to bad weather & network issue. Firm has assured to make 05 more schemes functional by 29.08.25. In some schemes displayed data is fluctuating & calibration of analyzer is required, their team is working on it.


Minutes of Meeting Date - 26-Aug-2025

Jackson Vishvaraj JV has integrated 32 schemes on JJM Portal against 01 HGJ Certified Schemes. 10 schemes are functional and other remaining schemes are non-functional due to bad weather, leakage & network issue. Firm has assured to make 02 more schemes functional by 01.09.25. In some schemes displayed data is fluctuating & calibration of analyzer is required, their team is working on it. 03 schemes will be integrated by 01.09.25


Minutes of Meeting Date - 02-Sep-2025

Jackson Vishvaraj JV has integrated 32 schemes on JJM Portal against 01 HGJ Certified Schemes. 13 schemes are functional and other remaining schemes are non-functional due to bad weather, leakage & network issue. Firm has assured to make 02 more schemes functional by 08.09.25. In some schemes displayed data is fluctuating & calibration of analyzer is required, their team is working on it. 01 scheme will be integrated by 08.09.25


Minutes of Meeting Date - 09-Sep-2025

Jackson Vishvaraj JV has integrated 33 schemes on JJM Portal against 01 HGJ Certified Schemes. 11 schemes are functional and other remaining schemes are non-functional due to bad weather, leakage & network issue. Firm has assured to make 02 more schemes functional by 15.09.25. In some schemes displayed data is fluctuating & calibration of analyzer is required, their team is working on it. 02 scheme will be integrated by 15.09.25


Minutes of Meeting Date - 16-Sep-2025

Jackson Vishvaraj JV has integrated 34 schemes on JJM Portal against 01 HGJ Certified Schemes. 11 schemes are functional and other remaining schemes are non-functional due to bad weather, leakage & network issue. Firm has assured to make 02 more schemes functional by 22.09.25. In some schemes displayed data is fluctuating & calibration of analyzer is required, their team is working on it. 01 scheme will be integrated by 22.09.25


Minutes of Meeting Date - 23-Sep-2025

Jackson Vishvaraj JV has integrated 35 schemes on JJM Portal against 01 HGJ Certified Schemes. 11 schemes are functional & 27 Schemes are live and functionality is unstable are non-functional due to bad weather, leakage & network issue. Firm has assured to make 02 more schemes functional by 29.09.25. In some schemes displayed data is fluctuating & calibration of analyzer is required, their team is working on it. 01 scheme will be integrated by 29.09.25


Minutes of Meeting Date - 07-Oct-2025

Jackson Vishvaraj JV has integrated 36 schemes on JJM Portal against 01 HGJ Certified Schemes. 14 schemes are functional & 30 Schemes are live and functionality is unstable are non-functional due to bad weather, leakage & network issue. Firm has assured to make 04 more schemes functional by 15.10.25. In some schemes displayed data is fluctuating & calibration of analyzer is required, their team is working on it. 03 scheme will be integrated by 15.10.25