Project Completion Plan


Minutes of Meeting Date - 01-Jul-2025

VSA has integrated 15 schemes on JJM Portal against 23 HGJ certified Schemes. 07 schemes are functional and 8 schemes are non-functional due to network issue. Firm has assured to make functional remaining all scheme till 15.07.25. Software troubleshooting is going on & all balance 08 schemes will be integrated by 31.07.25. 02 schemes will be integrated by 10.07.25.


Minutes of Meeting Date - 01-Jul-2025

VSA has integrated 15 schemes on JJM Portal against 23 HGJ certified Schemes. 07 schemes are functional and 8 schemes are non-functional due to network issue. Firm has assured to make functional remaining all scheme till 15.07.25. Software troubleshooting is going on & all balance 08 schemes will be integrated by 31.07.25. 02 schemes will be integrated by 10.07.25.


Minutes of Meeting Date - 01-Jul-2025

VSA has integrated 15 schemes on JJM Portal against 23 HGJ certified Schemes. 07 schemes are functional and 8 schemes are non-functional due to network issue. Firm has assured to make functional remaining all scheme till 15.07.25. Software troubleshooting is going on & all balance 08 schemes will be integrated by 31.07.25. 02 schemes will be integrated by 10.07.25.


Minutes of Meeting Date - 01-Jul-2025

VSA has integrated 15 schemes on JJM Portal against 23 HGJ certified Schemes. 07 schemes are functional and 8 schemes are non-functional due to network issue. Firm has assured to make functional remaining all scheme till 15.07.25. Software troubleshooting is going on & all balance 08 schemes will be integrated by 31.07.25. 02 schemes will be integrated by 10.07.25.


Minutes of Meeting Date - 01-Jul-2025

VSA has integrated 15 schemes on JJM Portal against 23 HGJ certified Schemes. 07 schemes are functional and 8 schemes are non-functional due to network issue. Firm has assured to make functional remaining all scheme till 15.07.25. Software troubleshooting is going on & all balance 08 schemes will be integrated by 31.07.25. 02 schemes will be integrated by 10.07.25.


Minutes of Meeting Date - 15-Jul-2025

VSA has integrated 25 schemes on JJM Portal against 23 HGJ certified Schemes. 10 schemes are functional and schemes are non-functional due to network issue. Firm has assured to make functional remaining all scheme till 1 25.07.25. Software troubleshooting is going on.. 02 schemes will be integrated by 25.07.25.


Minutes of Meeting Date - 29-Jul-2025

VSA has integrated 30 schemes on JJM Portal against 23 HGJ certified Schemes. 8 schemes are functional. Schemes are non-functional due to weather & network issue. Firm has assured to make functional 7 schemes by 8.08.25, 08 Schemes by 15.08.25 and remaining 07 schemes by 22.08.25. 01 scheme will be integrated by 08.08.25.


Minutes of Meeting Date - 05-Aug-2025

VSA has integrated 30 schemes on JJM Portal against 23 HGJ certified Schemes. 8 schemes were functional in last week but due to bad weather & network schemes became non functional. Firm has assured to make functional 8 schemes by 15.08.25 and 01 scheme will be integrated by 15.08.25


Minutes of Meeting Date - 12-Aug-2025

VSA has integrated 35 schemes on JJM Portal against 23 HGJ certified Schemes. 13 schemes were functional in last week but due to bad weather & network schemes became non functional. Integration target achieved. Firm has assured to make functional 7 schemes by 22.08.25


Minutes of Meeting Date - 19-Aug-2025

VSA has integrated 35 schemes on JJM Portal against 23 HGJ certified Schemes. 15 schemes are functional and other schemes are non functional due to bad weather & network issue. Integration target achieved. Firm has assured to make functional 7 schemes by 29.08.25


Minutes of Meeting Date - 26-Aug-2025

VSA has integrated 35 schemes on JJM Portal against 23 HGJ certified Schemes. 14 schemes are functional and other schemes are non functional due to bad weather & network issue. Several instruction given to firm but Functionality of OHT is not improved in this week, Firm has again assured to make functional 2 more schemes by 01.09.25 & 01 scheme will be integrated by 01.09.25


Minutes of Meeting Date - 02-Sep-2025

VSA has integrated 35 schemes on JJM Portal against 23 HGJ certified Schemes. 16 schemes are functional and other schemes are non functional due to bad weather & network issue. Several instruction given to firm. Firm has assured to make functional 2 more schemes by 08.09.25 & 01 scheme will be integrated by 08.09.25


Minutes of Meeting Date - 09-Sep-2025

VSA has integrated 35 schemes on JJM Portal against 23 HGJ certified Schemes. 17 schemes are functional and other schemes are non functional due to bad weather & network issue. Firm has assured to make functional 2 more schemes by 15.09.25 & 01 scheme will be integrated by 15.09.25


Minutes of Meeting Date - 16-Sep-2025

VSA has integrated 35 schemes on JJM Portal against 23 HGJ certified Schemes. 18 schemes are functional and other schemes are non functional due to bad weather & network issue. Firm has assured to make functional 2 more schemes by 22.09.25 & 01 scheme will be integrated by 22.09.25


Minutes of Meeting Date - 23-Sep-2025

VSA has integrated 35 schemes on JJM Portal against 23 HGJ certified Schemes. 18 schemes are functional & 23 shemes are live and other schemes are non functional due to bad weather & network issue. Firm has assured to make functional 2 more schemes by 29.09.25 & 01 scheme will be integrated by 29.09.25


Minutes of Meeting Date - 07-Oct-2025

VSA has integrated 35 schemes on JJM Portal against 23 HGJ certified Schemes. 13 schemes are functional & 20 shemes are live and other schemes are non functional due to bad weather & network issue. Firm has assured to make functional 2 more schemes by 13.10.25 & Firm has assured to integrate 01 scheme by 13.10.25


Minutes of Meeting Date - 27-Jan-2026

VSA-SCL JV has integrated 52 schemes on JJM Portal against 24 HGJ certified Schemes. 8 schemes are functional & 11 shemes are live and other schemes are non functional due to bad weather & network issue. Firm has assured to make functional 2 more scheme by 01.02.26 & Firm has assured to integrate 01 scheme by 01.02.26