Rithwik-Koya (JV) (Deoria)

Project Completion Plan


Minutes of Meeting Date - 24-Jun-2025

Ritwick Koya JV has completed integration of 07 schemes against 16 HGJ Schemes. Integration work remaining 9 schemes will be completed within a month. 01 schemes is functional and remaining 06 schemes are non functional due network issue. As per discussion with firm, troubleshooting is going on & will be completed within a week. Some data likes OHT water level, water(kl), Chlorine tank filling status, overall pump running hours are showing wrong or 0, calibration/rectification of these going on.


Minutes of Meeting Date - 24-Jun-2025

Ritwick Koya JV has completed integration of 07 schemes against 16 HGJ Schemes. Integration work remaining 9 schemes will be completed within a month. 01 schemes is functional and remaining 06 schemes are non functional due network issue. As per discussion with firm, troubleshooting is going on & will be completed within a week. Some data likes OHT water level, water(kl), Chlorine tank filling status, overall pump running hours are showing wrong or 0, calibration/rectification of these going on. Next week target is 3.


Minutes of Meeting Date - 01-Jul-2025

Ritwick Koya JV has integrated 12 schemes on JJM Portal against 16 HGJ Certified Schemes. Non schemes is functional and schemes are non-functional due network issue. Firm has assured to make all 12 remaining schemes functional by 20.07.25. Network troubleshooting is going on. Balance 04 schemes will be integrated by 20.07.25. 02 schemes will be integrated by 10.07.25.


Minutes of Meeting Date - 15-Jul-2025

Ritwick Koya JV has integrated 22 schemes on JJM Portal against 16 HGJ Certified Schemes. 02 schemes are functional and 20 schemes are non-functional due network issue. Firm has assured to make all schemes functional by 25.07.25. Network troubleshooting is going on. 02 Schemes will be integrated by 25.07.25


Minutes of Meeting Date - 29-Jul-2025

Ritwick Koya JV has integrated 23 schemes on JJM Portal against 17 HGJ Certified Schemes. 08 schemes are functional and other schemes are non-functional due to bad weather & network issue. Firm has assured to make 07 more schemes functional by 08.08.25. Network troubleshooting is going on. 02 Schemes will be integrated by 08.08.25


Minutes of Meeting Date - 05-Aug-2025

Ritwick Koya JV has integrated 23 schemes on JJM Portal against 17 HGJ Certified Schemes. 05 schemes are functional and other schemes are non-functional due to bad ewather & network issue. Firm has assured to make 07 more schemes functional by 15.08.25 Network troubleshooting is going on. 01 Schemes will be integrated by 15.08.25


Minutes of Meeting Date - 12-Aug-2025

Koya (JV) Ritwick Koya JV has integrated 23 schemes on JJM Portal against 18 HGJ Certified Schemes. 08 schemes are functional and other schemes are non-functional due to bad ewather & network issue. Firm has assured to make 05 more schemes functional by 22.08.25 Network troubleshooting is going on.


Minutes of Meeting Date - 19-Aug-2025

Koya (JV) Ritwick Koya JV has integrated 23 schemes on JJM Portal against 18 HGJ Certified Schemes. 07 schemes are functional and other schemes are non-functional due to bad ewather & network issue. Firm has assured to make 05 more schemes functional by 29.08.25


Minutes of Meeting Date - 19-Aug-2025

Koya (JV) Ritwick Koya JV has integrated 23 schemes on JJM Portal against 18 HGJ Certified Schemes. 07 schemes are functional and other schemes are non-functional due to bad ewather & network issue. Firm has assured to make 05 more schemes functional by 29.08.25


Minutes of Meeting Date - 19-Aug-2025

Koya (JV) Ritwick Koya JV has integrated 23 schemes on JJM Portal against 18 HGJ Certified Schemes. 07 schemes are functional and other schemes are non-functional due to bad ewather & network issue. Firm has assured to make 05 more schemes functional by 29.08.25


Minutes of Meeting Date - 19-Aug-2025

Koya (JV) Ritwick Koya JV has integrated 23 schemes on JJM Portal against 18 HGJ Certified Schemes. 07 schemes are functional and other schemes are non-functional due to bad ewather & network issue. Firm has assured to make 05 more schemes functional by 29.08.25


Minutes of Meeting Date - 26-Aug-2025

Koya (JV) Ritwick Koya JV has integrated 23 schemes on JJM Portal against 18 HGJ Certified Schemes. 09 schemes are functional and other schemes are non-functional due to bad ewather & network issue. Firm has assured to make 05 more schemes functional by 01.09.25


Minutes of Meeting Date - 02-Sep-2025

Ritwick Koya JV has integrated 23 schemes on JJM Portal against 18 HGJ Certified Schemes. 09 schemes are functional and other schemes are non-functional due to bad ewather & network issue. Firm has assured to make 04 more schemes functional by 08.09.25. 01 scheme will be integrated by 09.09.25


Minutes of Meeting Date - 09-Sep-2025

Ritwick Koya JV has integrated 23 schemes on JJM Portal against 17 HGJ Certified Schemes. 07 schemes are functional and other schemes are non-functional due to bad ewather & network issue. Firm has assured to make 04 more schemes functional by 15.09.25. 01 scheme will be integrated by 15.09.25


Minutes of Meeting Date - 16-Sep-2025

Ritwick Koya JV has integrated 23 schemes on JJM Portal against 18 HGJ Certified Schemes. 06 schemes are functional and other schemes are non-functional due to bad ewather & network issue. Firm has assured to make 03 more schemes functional by 22.09.25. 01 scheme will be integrated by 22.09.25


Minutes of Meeting Date - 23-Sep-2025

Ritwick Koya JV has integrated 23 schemes on JJM Portal against 18 HGJ Certified Schemes. 07 schemes are functional and other schemes are non-functional due to bad ewather & network issue. Firm has assured to make 03 more schemes functional by 29.09.25. 01 scheme will be integrated by 29.09.25


Minutes of Meeting Date - 07-Oct-2025

Ritwick Koya JV has integrated 23 schemes on JJM Portal against 18 HGJ Certified Schemes. 07 schemes are functional and other schemes are non-functional due to bad ewather & network issue. Firm has assured to make 03 more schemes functional by 13.10.25. Firm has assured to integrate 01 scheme by 13.10.25