Procurement of material and instruments are still pending since last 04 weeks of given assurances ,presently only purchase order has been recieved. on 22nd of july,by which as confirmation of Md bgcc expected date of completion for SCADA integration of intake/wtp/Cwrs along with all Ohts will be 30.09.2025.
Intake and WTP is integrated with SCADA and shown connected on SCADA portal and all CWR and ESR not connected to SCADA because related material dor SCADA is not installed and prior given date by BGCC was 30/09/25 but till date no work done site.
Last date for completion of SCADA automation with integration and data verification which was 30.09.2025 as given by MD BGCC has been already lapsed. Still supply of main SCADA material is pending along with RTUs room. MD BGCC again assured to complete it overall with SCADA integration within 02 months, presently no microplan have been submitted regarding such assurances after several reminders.