Procurement of material and instruments are still pending since last 04 weeks of given assurances ,presently only purchase order has been recieved. on 22nd of july,by which as confirmation of Md bgcc expected date of completion for SCADA integration of intake/wtp/Cwrs along with all Ohts will be 30.09.2025.
Procurement of material and instruments are still pending since last 04 weeks of given assurances ,presently only purchase order has been recieved. on 22nd of july,by which as confirmation of Md bgcc expected date of completion for SCADA integration of intake/wtp/Cwrs along with all Ohts will be 30.09.2025.
Intake and WTP is integrated with SCADA but data not shown on portal and all CWR and ESR not connected to SCADA because related material dor SCADA is not installed and prior given date by BGCC was 30/09/25 but till date no work done site.