all CWRs are now showing connected to SCADA integration portal that was in problem mode. all data is visible and verified by NCC PM .
Water logging in OHT 5 from last 3 days due to heavy rain so for safety purpose supply was stopped from OHT 5 till now and resume water supply within 2 days s as per NCC DGM.
OHTs 1, 2, 3, 5, 6 and OHT 7 are not showing data on SCADA portal due to network issue so yesterday total water supply is shown as 4.75% and rectification work in progress as per DGM NCC.
00 no of OHT is shown less then 75% and 00 no of OHT is shown more then 150% but overall water supply shown 110%. All CWRs are connected to SCADA