      Ahugi Kalan GOV (8010572)

Project Completion Plan


Minutes of Meeting Date - 26-Aug-2025

All OHT made functional on portal . Data of Intake , WTP, CWR and 14 OHT has been verified . Firm again comitted that Remaining OHTs instruments data are being check for calibration and will be completed till 5.9.25


Minutes of Meeting Date - 02-Sep-2025

All OHT made functional on portal . Data of Intake , WTP, CWR and 25 OHT has been verified . Remaining OHTs instruments data are being check for calibration and will be completed till 15.9.25


Minutes of Meeting Date - 09-Sep-2025

All OHT made functional on portal . Data of Intake , WTP, CWR and 25 OHT has been verified . Remaining OHTs instruments data are being check for calibration and will be completed till 15.9.25


Minutes of Meeting Date - 16-Sep-2025

All OHT made functional on portal . Data of Intake , WTP, CWR and 24 OHT has been verified . Remaining OHTs instruments data are being check for calibration and will be completed till 30.9.25


Minutes of Meeting Date - 23-Sep-2025

All OHT made functional on portal . Data of Intake , WTP, CWR and 24 OHT has been verified . Remaining OHTs instruments data are being check for calibration and will be completed till 30.9.25