Check List Form

      Khatan GOV (8044758)

Project Completion Plan


Minutes of Meeting Date - 24-Jun-2025

Solar and instruments installation work in progress at OHTs. Assurance by firm- All OHTs- will be integrated and functional on portal by 10.07.2025. Verification of OHTs by 15.07.2025.


Minutes of Meeting Date - 24-Jun-2025

Data of 51 nos. OHTs are showing in Master Control Station at WTP. Solar and instruments testing & commissioning work in progress at remaining OHTs. Only one team is available at site. Assurance by firm- All 116 Nos. OHTs- will be integrated and functional on portal by 10.07.2025. Verification of OHTs by 15.07.2025.


Minutes of Meeting Date - 08-Jul-2025

Slow progress in functionality. Assurance by firm- All 116 Nos. OHTs- will be integrated and functional on portal by 10.07.2025. Verification of OHTs by 15.07.2025.