Only one team is available at site. Solar installation work in progress. Assurance by firm- All OHTs will be integrated and functional on portal by 30.06.2025.
As per the instruction, notice regarding slow progress of automation & integration work is to be issued. Assurance by firm- Solar installation work in progress. All OHTs will be integrated and functional on portal by 05.07.2025.
Revised plan needs to be submitted by firm. Solar panel installation team is now available at site and all 17nos. OHT will be integrated on portal by 15.07.2025.
Due to rain Solar panel installation work disturbed and again revised date committed by firm. All 17nos. OHT will be integrated and functional on portal by 20.07.2025.
Slow progress in Solar panel installation work at OHT. Again revised date committed by firm. that all 17 nos. OHT will be integrated and functional on portal by 30.07.2025.
Very slow progress in installation of solar panels at OHT. Again revised date committed by firm. that all 17 nos. OHT will be integrated and functional on portal by 31.07.2025.
Installation of solar panels completed at 08 nos. OHT and revised date committed by firm, that all 17 nos. OHT will be functional and verified on portal by 15.08.2025.
Installation of solar panels completed at 12 nos. OHT and revised date committed by firm, that all 17 nos. OHT will be functional and verified on portal by 20.08.2025.
Integration Work completed. Due to network problem disconnection is happening. Stable connection is required and Calibration needs to be done. All 17 OHTs will be functional on portal by 31.08.2025.