Only one team is available at site. Instrument installation work in progress at WTP. Assurance by firm- Intake and WTP will be functional by 25.06.2025 and all functional OHTs-51 Nos. will be integrated and functional on portal by 15.07.2025.
As per the instruction, notice regarding non compliance of targeted work that is integration of Intake & WTP on portal by 25.06.2025 and zero progress in integration of Functional OHTs is to be issued. Assurance by firm- Vendor Team available at WTP, by 29.06.2025 Intake & WTP will be integrated on portal. All functional OHTs-51 Nos. will be integrated and functional on portal by 15.07.2025.
Revised plan needs to be submitted by firm. Solar panel installation team is now available at site and 16 nos. OHT will be integrated on portal by 15.07.2025.