Installation at 17 nos. OHTs completed. Only one team is available at site. Assurance by firm- All functional OHTs-23 Nos. will be integrated and functional on portal by 30.06.2025.
As per the instruction, notice regarding slow progress of automation & integration work is to be issued. Installation work at 22 nos. OHTs are completed. Only one team is available at site. Assurance by firm- All functional OHTs-23 Nos. will be integrated & functional on portal by 30.06.2025. Remaining 02 Nos. (non functional) by 05.07.2025 + 03 Nos. (under construction) will be completed by 31.07.2025.
Assurance by firm- All functional OHTs-23 Nos. will be integrated & functional on portal by 15.07.2025. Remaining 02 Nos. (non functional) by 20.07.2025 + 03 Nos. (under construction) will be completed by 31.07.2025.
Assurance by firm- All functional OHTs-23 Nos. will be integrated & functional on portal by 15.07.2025. Remaining 02 Nos. (non functional) by 20.07.2025 + 03 Nos. (under construction) will be completed by 31.07.2025
Assurance by firm- All functional OHTs-23 Nos. will be integrated & functional on portal by 25.07.2025. Remaining 02 Nos. (non functional) by 30.07.2025 + 03 Nos. (under construction) will be completed by 10.08.2025
Due to a fault in the master control station (Server) at WTP, data has not been coming on portal since 21.07.2025. Firm committed that it would be resolved by 31.07.2025 and if not then department can take any action.
Due to a fault in the master control station (Server) at WTP, data has not been coming on portal since 21.07.2025. Firm committed that it would be resolved by 02.08.2025.
Due to a fault in the master control station (Server) at WTP, data has not been coming on portal continuously since 21.07.2025. Firm committed that it would be resolved by 10.08.2025 and all OHT will be integrated and functional on portal.
Installation of solar panels completed at 23 nos. OHT and revised date committed by firm, that all 23 OHT will be functional and verified on portal by 31.08.2025.