Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in
Check List Form

      Haraulipur GOV and Tubewell Scheme 125 Nos. (8135500)

Project Completion Plan


Minutes of Meeting Date - 24-Jun-2025

All OHTs of Surface scheme (12 Nos.) will be functional on portal by 30.06.2025. Ground water related schemes (118 Nos.) will be functional on portal by 30.08.2025 as per completion plan submitted by firm. Material/Equipment's for 10 Nos. OHT procured at site and installation work will be start from 22.06.2025.


Minutes of Meeting Date - 24-Jun-2025

As per the instruction, notice regarding slow progress of automation & integration work is to be issued. Assurance by firm- All OHTs of Surface scheme (12 Nos.) will be functional on portal by 30.06.2025. Ground water related schemes (118 Nos.) will be functional on portal by 30.08.2025 as per completion plan submitted by firm. Material/Equipment's for 10 Nos. OHT procured at site and installation work started at 02 no. OHTs.


Minutes of Meeting Date - 08-Jul-2025

All OHTs of Surface scheme (12 Nos.) will be functional on portal by 10.07.2025. Ground water related schemes (118 Nos.) will be functional on portal by 30.08.2025 as per completion plan submitted by firm. Material/Equipment's for 10 Nos. OHT procured at site and installation work in progress at 02 no. OHTs.


Minutes of Meeting Date - 15-Jul-2025

No instrument installation team available at sites. Ground water related schemes (118 Nos.) will be functional on portal by 30.08.2025 as per completion plan submitted by firm. Only Material/Equipment's for 10 Nos. OHT procured at site.


Minutes of Meeting Date - 22-Jul-2025

Instrument installation work in progress at 04 no. OHT, Assurance by firm- 10 nos. OHT will be integrated and functional on portal by 31.07.2025. Material/equipment's not available for remaining 108 nos. OHTs.


Minutes of Meeting Date - 29-Jul-2025

Instrument installation work in progress at 06 no. OHT of ground water. Assurance by firm- 10 nos. OHT will be integrated and functional on portal by 05.08.2025. Revised micro plan need to be submit for remaining 108 nos. OHTs.


Minutes of Meeting Date - 05-Aug-2025

Instrument installation work in progress at 06 no. OHT of ground water. Assurance by firm- 10 nos. OHT will be integrated and functional on portal by 10.08.2025. Revised micro plan need to be submit for remaining 108 nos. OHTs.


Minutes of Meeting Date - 19-Aug-2025

Instrument installation work in progress at 10 no. OHT of ground water. Assurance by firm- 10 nos. OHT will be integrated and functional on portal by 15.08.2025. Revised micro plan need to be submit for remaining 108 nos. OHTs.


Minutes of Meeting Date - 26-Aug-2025

Instrument installation work in progress at 10 no. OHT of ground water. Assurance by firm- 10 nos. OHT will be integrated and functional on portal by 31.08.2025. Revised micro plan need to be submit for remaining 108 nos. OHTs.


Minutes of Meeting Date - 16-Sep-2025

Stable connection is required for disconnected OHTs of Surface schemes-12 nos. OHT. Work stopped in Ground water supply schemes due to permission issue from top management of firm. Revised micro plan need to be submit for remaining 118 nos. OHTs.


Minutes of Meeting Date - 23-Sep-2025

No engineer is available at site for attending issues of disconnection. Stable connection is required for disconnected OHTs of Surface scheme. Revised date committed by the firm that order placed for 118 OHTs of Ground water supply schemes and supply begins from 25.09.2025. Revised micro plan need to be submit to office.