      Haraulipur GOV and Tubewell Scheme 125 Nos. (8135500)

Project Completion Plan


Minutes of Meeting Date - 24-Jun-2025

All OHTs of Surface scheme (12 Nos.) will be functional on portal by 30.06.2025. Ground water related schemes (118 Nos.) will be functional on portal by 30.08.2025 as per completion plan submitted by firm. Material/Equipment's for 10 Nos. OHT procured at site and installation work will be start from 22.06.2025.


Minutes of Meeting Date - 24-Jun-2025

As per the instruction, notice regarding slow progress of automation & integration work is to be issued. Assurance by firm- All OHTs of Surface scheme (12 Nos.) will be functional on portal by 30.06.2025. Ground water related schemes (118 Nos.) will be functional on portal by 30.08.2025 as per completion plan submitted by firm. Material/Equipment's for 10 Nos. OHT procured at site and installation work started at 02 no. OHTs.


Minutes of Meeting Date - 08-Jul-2025

All OHTs of Surface scheme (12 Nos.) will be functional on portal by 10.07.2025. Ground water related schemes (118 Nos.) will be functional on portal by 30.08.2025 as per completion plan submitted by firm. Material/Equipment's for 10 Nos. OHT procured at site and installation work in progress at 02 no. OHTs.


Minutes of Meeting Date - 15-Jul-2025

No instrument installation team available at sites. Ground water related schemes (118 Nos.) will be functional on portal by 30.08.2025 as per completion plan submitted by firm. Only Material/Equipment's for 10 Nos. OHT procured at site.


Minutes of Meeting Date - 22-Jul-2025

Instrument installation work in progress at 04 no. OHT, Assurance by firm- 10 nos. OHT will be integrated and functional on portal by 31.07.2025. Material/equipment's not available for remaining 108 nos. OHTs.


Minutes of Meeting Date - 29-Jul-2025

Instrument installation work in progress at 06 no. OHT of ground water. Assurance by firm- 10 nos. OHT will be integrated and functional on portal by 05.08.2025. Revised micro plan need to be submit for remaining 108 nos. OHTs.


Minutes of Meeting Date - 05-Aug-2025

Instrument installation work in progress at 06 no. OHT of ground water. Assurance by firm- 10 nos. OHT will be integrated and functional on portal by 10.08.2025. Revised micro plan need to be submit for remaining 108 nos. OHTs.


Minutes of Meeting Date - 19-Aug-2025

Instrument installation work in progress at 10 no. OHT of ground water. Assurance by firm- 10 nos. OHT will be integrated and functional on portal by 15.08.2025. Revised micro plan need to be submit for remaining 108 nos. OHTs.


Minutes of Meeting Date - 26-Aug-2025

Instrument installation work in progress at 10 no. OHT of ground water. Assurance by firm- 10 nos. OHT will be integrated and functional on portal by 31.08.2025. Revised micro plan need to be submit for remaining 108 nos. OHTs.