All OHTs of Surface scheme (12 Nos.) will be functional on portal by 30.06.2025. Ground water related schemes (118 Nos.) will be functional on portal by 30.08.2025 as per completion plan submitted by firm. Material/Equipment's for 10 Nos. OHT procured at site and installation work will be start from 22.06.2025.
As per the instruction, notice regarding slow progress of automation & integration work is to be issued. Assurance by firm- All OHTs of Surface scheme (12 Nos.) will be functional on portal by 30.06.2025. Ground water related schemes (118 Nos.) will be functional on portal by 30.08.2025 as per completion plan submitted by firm. Material/Equipment's for 10 Nos. OHT procured at site and installation work started at 02 no. OHTs.
All OHTs of Surface scheme (12 Nos.) will be functional on portal by 10.07.2025. Ground water related schemes (118 Nos.) will be functional on portal by 30.08.2025 as per completion plan submitted by firm. Material/Equipment's for 10 Nos. OHT procured at site and installation work in progress at 02 no. OHTs.