Only 25 ohts scada works has been completed which data could not be verified due to sensor fault will be resolved by 06 of august and rest 31 Ohts willbe integrated on august 25th as confirmation of state head of Gvpr.
25nos OHT (23 nos complete and 2 nos installed but not integrated) integration work completed but data is not stable so data has not been verified and other remaining oht integration work is in progress expected date of completion for scada integration of remaining oht (31 nos) dt. 15.09.2025 as per confirmation of state head GVPR