Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in
Check List Form

      Kota Mustakil GOV and Tubewell Scheme 270 Nos. (8135522)

Project Completion Plan


Minutes of Meeting Date - 01-Jul-2025

partial scada material procurement by the firm and balance material and instruement are pending only plc panel are installed at site. any component of site is not scada integrated by the firm expected date of completion for scada integration of intake/WTP dt. 15.09.2025 & expected date of completion for scada integration of cwr & oht dt. 30.09.2025 as per confirmation of state head BGCC