Procurement of material and instruments are still pending since last 04 weeks of given assurances ,presently only purchase order has been recieved. on 22nd of july,by which as confirmation of Md bgcc but supply is still pending till now. expected date of completion for SCADA integration of intake/wtp/Cwrs along with all Ohts will be 30.09.2025.
Last date for completion of scada automation with integration and data verification which was 30 -09 -2025 as given by MD BGCC, has been already lapsed , still supply of main scada material is pending along with RTUs room . Md BGCC again assured to complete it overall with scada integration within two months, presently no micro plans have been submitted regarding such assurances after several reminders .