Partial SCADA material procurement by the firm and balance material and instruments are pending. Only plc panel are installed at site. No one site is integrated by SCADA. Firm expected date of completion for SCADA integration of intake/WTP till 15.08.2025 & expected date of completion for SCADA integration of CWrs & OHTs till 30.08.2025 as per confirmation of state head BGCC.
Procurement of material and instruments are still pending since last 04 weeks of given assurances ,presently only purchase order has been recieved. on 22nd of july,by which as confirmation of Md bgcc expected date of completion for SCADA integration of intake/wtp/Cwrs along with all Ohts will be 30.09.2025.
Procurement of material and instruments are still pending since last 04 weeks of given assurances ,presently only purchase order has been recieved. on 22nd of july,by which as confirmation of Md bgcc expected date of completion for SCADA integration of intake/wtp/Cwrs along with all Ohts will be 30.09.2025.
Note: 1= Supply 2= Installation 3= Commissioning & Integration As per conformation of State Head BGCC, action plans are forllowing: Intake: 1= Completed 2= 20/08/25 3= 05/09/25 WTP 1= Completed 2= 15/08/25 3= 30/08/25 All CWRs 1= 30/08/25 2= 15/09/25 3= 30/09/25 All OHTs 1= 30/08/25 2= 15/09/25 3= 30/09/25