Partial SCADA material procurement by the firm and balance material and instruments are pending. Only plc panel are installed at site. No one site is integrated by SCADA. Firm expected date of completion for SCADA integration of intake/WTP till 30.07.2025 & expected date of completion for SCADA integration of CWRs & OHTs till 15.09.2025 as per confirmation of state head BGCC.
Procurement of material and instruments are still pending since last 04 weeks of given assurances ,presently only purchase order has been recieved. on 22nd of july,by which as confirmation of Md bgcc expected date of completion for SCADA integration of intake/wtp/Cwrs along with all Ohts will be 30.09.2025.
Intake and WTP, SCADA installation work is progress from last 20 days but not integrated till date and all CWR and ESR not connected to SCADA because only 1 team is available on site and related material for SCADA is not recieved and installed on site and prior given date by BGCC was 30/09/25 but till date no work done site.