Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in
Check List Form

      Barthari GOV (8135956)

Project Completion Plan


Minutes of Meeting Date - 01-Jul-2025

Partial SCADA material procurement by the firm and balance material and instruments are pending. Only plc panel are installed at site. No one site is integrated by SCADA. Firm expected date of completion for SCADA integration of intake/WTP till 30.07.2025 & expected date of completion for SCADA integration of CWRs & OHTs till 15.09.2025 as per confirmation of state head BGCC.


Minutes of Meeting Date - 04-Nov-2025

Intake and WTP, SCADA installation work is progress from last 20 days but not integrated till date and all CWR and ESR not connected to SCADA because only 1 team is available on site and related material for SCADA is not recieved and installed on site and prior given date by BGCC was 30/09/25 but till date no work done site.


Minutes of Meeting Date - 25-Nov-2025

Last date for completion of SCADA automation with integration and data verification which was 30.09.2025 as given by MD BGCC has been already lapsed. Still supply of main SCADA material is pending along with RTUs room. MD BGCC again assured to complete it overall with SCADA integration within 02 months, presently no microplan have been submitted regarding such assurances after several reminders.