Installation of instruments at 21 nos. OHTs completed. Assurance by firm- All OHTs will be integrated and functional on portal by 30.06.2025. No action regarding integration of CWRs.
As per the instruction, notice regarding slow progress of automation & integration work is to be issued. No action regarding integration of CWRs. Assurance by firm- Installation of instruments at 23 nos. OHTs completed. Vendor team is now available at WTP for integration of OHTs and make them functional. All 29 nos. OHTs will be integrated and functional on portal by 05.07.2025 and CWRs by 10.07.2025.
Team is now available at WTP for integration of OHTs. All 29 nos. OHTs will be integrated and functional on portal by 15.07.2025. Data Verification work in progress.
Installation of solar panel and integration work is completed in 28 Nos OHT. Assurance by firm - all 29 OHTs will be integrated and functional on portal by 25.07.2025. Data Verification work in progress.
Calibration of flowmeter is required. Data is not continiously coming on portal from site. Assurance by firm- Rectification work in progress and all OHTs will be integrated and functional on portal by 31.07.2025.
Calibration of flowmeter is required. Data is not continiously coming on portal from site. Assurance by firm- Rectification work in progress and all OHTs will be integrated and functional on portal by 10.08.2025
Calibration of flowmeter is required. Data is not continiously coming on portal from site. Assurance by firm- Rectification work in progress and all OHTs will be integrated and functional on portal by 20.08.2025