Installation of instruments at 21 nos. OHTs completed. Assurance by firm- All OHTs will be integrated and functional on portal by 30.06.2025. No action regarding integration of CWRs.
As per the instruction, notice regarding slow progress of automation & integration work is to be issued. No action regarding integration of CWRs. Assurance by firm- Installation of instruments at 23 nos. OHTs completed. Vendor team is now available at WTP for integration of OHTs and make them functional. All 29 nos. OHTs will be integrated and functional on portal by 05.07.2025 and CWRs by 10.07.2025.
Team is now available at WTP for integration of OHTs. All 29 nos. OHTs will be integrated and functional on portal by 15.07.2025. Data Verification work in progress.