10 OHT were made functional earlier . Firm committed again to make Remaining 2 Nos. OHT functional till 30.8.25 . Also Residual Chlorine analyzer value are not being transfered to portal yet though it was committed to complete it till 3.8.25.
12 OHT has been made functional on portal . Firm committed again to get verify the instruments data till 12.9.25 . Residual Chlorine analyzer value are not being transfered to portal yet though it was committed to complete it till 3.8.25.
All OHT has been made functional on portal . Firm again commited that all instruments will be calibrated and integrated till 12.9.25. But Components instrument value are either constant or zero yet. Firm again committed to verify data till 20.9.25 also OHTs RCA value shall be updated till 20.9.25 .
All OHT has been made functional on portal . 2 nos. EMF configuration & NRV installation are required . same shall be rectify till 26.9.25 .
All OHT has been made functional on portal . 2 nos. EMF configuration & NRV installation are required . same shall be rectify till 26.9.25 . Instruments Calibration & commissioning activity are slow causing non verification of components .
All OHT has been made functional on portal . 2 nos. EMF configuration & NRV installation are required . same shall be rectify till 26.9.25 . Instruments Calibration & commissioning activity are slow causing non verification of components . No progress are being provided in Integration work .