All 48 OHT has been made functional on portal . Firm commited to calibrat 24 nos. installed instruments till 31.8.25 and remaining 24 nos. till 8.9.25 . Calibration work to be expedite .
All 48 OHT has been made functional on portal . Firm has to be calibrate and verify the data till 8.9.25 . Intake well, WTP, OHT instruments data are constant . CWR instruments data are zero .
All 48 OHT has been made functional on portal . Firm has to be calibrate and verify the data till 8.9.25 . Intake well, WTP, OHT instruments data are constant . CWR instruments data are zero . Configuration are not being done . Firm again committed to complete the same till 30.9.25
All 48 OHT has been made functional on portal . Configuration are not being done . Firm again committed to complete the same till 30.9.25 . Data correction work are not being started causing non verification of data .
All 48 OHT has been made functional on portal . Intake well, WTP, OHT instruments data are constant . CWR instruments data are zero . Configuration are not being done . As per recommitment same should have completed till 30.9.25 . Firm again commite to expedite and complete the same till 12.11.25
All 48 OHT has been made functional on portal . Intake well, WTP, OHT instruments data are constant . CWR instruments data are zero . Configuration are not being done . As per recommitment same should have completed till 30.9.25 . Firm again commited to expedite and complete the same till 12.11.25 .
All 48 OHT has been made functional on portal . Intake well, WTP, OHT instruments data are constant . CWR instruments data are zero . Configuration are not being done . As per recommitment same should have completed till 30.9.25 . Firm again commited to expedite and complete the same till 12.11.25 .
All 48 OHT has been made functional on portal . Intake well, WTP, OHT instruments data are constant . CWR instruments data are zero . As per recommitment same should have completed till 30.9.25 . Firm again commited to expedite and complete the same till 12.11.25 . Work status are same as previous & to be expedite .
All 48 OHT has been made functional on portal . Intake well, WTP, OHT instruments data are constant . CWR instruments data are zero . As per recommitment same should have completed till 12.11.25 . Work status are same as previous & to be expedite .
All 48 OHT has been made functional on portal . Intake well, WTP, OHT instruments data are constant . CWR instruments data are zero . As per recommitment same should have completed till 12.11.25 . Work status are same as previous & to be expedite .
All 48 OHT has been made functional on portal . Intake well, WTP, OHT instruments data are constant . CWR instruments data are zero . As per recommitment same should have completed till 12.11.25 . Work status are same as previous & to be expedite .
All 48 OHT has been made functional on portal . Intake well, WTP, OHT instruments data are constant . CWR instruments data are zero . As per recommitment same should have completed till 12.11.25 . Work status are same as previous & to be expedite .
All 48 OHT has been made functional on portal . WTP, CWR, OHT instruments data are either zero/ constant or unstable . As per recommitment same should have completed till 12.11.25 . Work progress are to be expedite .
All 48 OHT has been made functional on portal . Intake well, OHT instruments data are constant . CWR instruments data are zero . As per recommitment same should have completed till 12.11.25 . Work status are same as previous & to be expedite .
All 48 OHT has been made functional on portal . Intake well, OHT instruments data are constant . CWR instruments data are zero . As per recommitment same should have completed till 12.11.25 . Work status are same as previous & to be expedite .
All 48 OHT has been made functional on portal . OHT instruments data are constant . CWR instruments data are zero . As per recommitment same should have completed till 12.1.26 . Work status are same as previous & to be expedite .
All 48 OHT has been made functional on portal . OHT instruments data are constant . CWR instruments data are zero . As per recommitment same should have completed till 12.1.26 . Work status are same as previous & to be expedite .
All 48 OHT has been made functional on portal . 30 nos. OHT has been verified . CWR instruments data are zero . As per recommitment same should have completed till 12.4.26 . Integration Work to be expedite .
All 48 OHT has been made functional on portal . 30 nos. OHT has been verified . CWR instruments data are zero . As per recommitment same should have completed till 12.4.26 . Integration Work to be expedite . Work status are same as previous .
102 OHt has been made functional . As per Firm recommitment calibration & verification should have completed till 17.2.26 . 55 nos. OHT has been verified yet . Dedicated team required . Verification are being done & calibration has to be expedite.
102 OHt has been made functional . As per Firm recommitment calibration & verification should have completed till 17.2.26 . 55 nos. OHT has been verified yet . Dedicated team required . calibration activity are not being enhance . Integration work to expedite .
102 OHt has been made functional . As per Firm recommitment calibration & verification should have completed till 17.2.26 . 55 nos. OHT has been verified yet . Dedicated team required . calibration activity are not being enhance . Integration work to expedite .
All 48 OHT has been made functional on portal . 30 nos. OHT has been verified . CWR instruments data are zero . As per recommitment same should have completed till 12.4.26 . Seprate team not available for integration work . Integration Work to be expedite .
All 48 OHT has been made functional on portal . 30 nos. OHT has been verified . CWR instruments data are zero . As per recommitment same should have completed till 12.4.26 .team not available for integration work . 3 OHT are functional since last 10 days .
All 48 OHT has been made functional on portal . 30 nos. OHT has been verified . CWR instruments data are zero . As per recommitment same should have completed till 12.4.26 .team not available for integration work . All OHT are non functional since last 15 days .
All 48 OHT has been made functional on portal . 30 nos. OHT has been verified . CWR instruments data are zero . As per recommitment same should have completed till 12.4.26 .team not available for integration work . All OHT are non functional since last 21 days .