It was commited that Communication issue will be resolve & 11 disconnected OHT shall be made functional till 6.8.25 . Also remaining 18 non integrated OHT shall be integrated and become functional on portal till 15.8.25 . Firm again comitted to integrat remaining 14 nos. OHT till 31.8.25.
87 OHt has been made functional, 9 OHT are disconnected and 6 OHT are non integrated . 7 OHT shall be reflected as functional till 9.9.25. Remaining 8 OHT shall be functional till 15.9.25. Functional Component values are either constant or zero which has to be corrected on portal .
91 OHt has been made functional, 9 OHT are disconnected and 2 OHT are non integrated . Due to modem issue data of some EMF are not being transferred , again committed that 7 OHT shall be made functional till 22.9.25. and Remaining 4 OHT shall be functional till 28.9.25.
95 OHt has been made functional, 4 OHT are disconnected and 3 OHT are non integrated . Due to modem issue data of some EMF are not being transferred , again committed that 4 disconnected OHT & 3 non integrated shall be made functional till 30.9.25.
95 OHt has been made functional, 4 OHT are disconnected and 3 OHT are non integrated . Due to modem issue data of some EMF are not being transferred , again committed that 4 disconnected OHT & 3 non integrated shall be made functional till 30.9.25. Integration status are same as previous week . Work to be expedite
95 OHt has been made functional, 4 OHT are disconnected and 3 OHT are non integrated . Due to modem issue data of some EMF are not being transferred , again committed that 4 disconnected OHT & 3 non integrated shall be made functional till 2.2. 10.25.
95 OHt has been made functional, 4 OHT are disconnected and 3 OHT are non integrated . Due to modem issue data of some EMF are not being transferred ,Firm again committed that 2 non integrated shall be made integrated & Remaining disconnected OHT shall be made functional till 28.10.25 and 31. 10.25 respectively .
95 OHt has been made functional, 4 OHT are disconnected and 3 OHT are non integrated . Due to modem issue data of some EMF are not being transferred ,Firm again committed that 2 non integrated shall be made integrated & Remaining disconnected OHT shall be made functional till 28.10.25 and 31. 10.25 respectively . Firm again committed to integrate remaining OHT till 7.11.25
95 OHt has been made functional, 4 OHT are disconnected and 2 OHT are non integrated. Firm again committed that 2 non integrated & Remaining disconnected OHT shall be made functional till 6.11.25 .
97 OHt has been made functional, 5 OHT are disconnected , Firm again committed that Remaining disconnected OHT shall be made functional till 7.11.25 .
97 OHt has been made functional, 5 OHT are disconnected , Firm again committed that Remaining disconnected OHT shall be made functional till 7.11.25 . Work Status are same as previous .