It was commited that Communication issue will be resolve & 11 disconnected OHT shall be made functional till 6.8.25 . Also remaining 18 non integrated OHT shall be integrated and become functional on portal till 15.8.25 . Firm again comitted to integrat remaining 14 nos. OHT till 31.8.25.
87 OHt has been made functional, 9 OHT are disconnected and 6 OHT are non integrated . 7 OHT shall be reflected as functional till 9.9.25. Remaining 8 OHT shall be functional till 15.9.25. Functional Component values are either constant or zero which has to be corrected on portal .
91 OHt has been made functional, 9 OHT are disconnected and 2 OHT are non integrated . Due to modem issue data of some EMF are not being transferred , again committed that 7 OHT shall be made functional till 22.9.25. and Remaining 4 OHT shall be functional till 28.9.25.
95 OHt has been made functional, 4 OHT are disconnected and 3 OHT are non integrated . Due to modem issue data of some EMF are not being transferred , again committed that 4 disconnected OHT & 3 non integrated shall be made functional till 30.9.25.
95 OHt has been made functional, 4 OHT are disconnected and 3 OHT are non integrated . Due to modem issue data of some EMF are not being transferred , again committed that 4 disconnected OHT & 3 non integrated shall be made functional till 30.9.25. Integration status are same as previous week . Work to be expedite