Check List Form

      Nagawan GOV (8175013)

Project Completion Plan


Minutes of Meeting Date - 19-Aug-2025

It was commited that V set to be procured for OHT no. 6, 7, 8 & integration will be completed as below ;- OHT nos. 5, 6, 7, 8 till 25.8.25 & OHT no. 3 till 12.8.25. Work not completed and again commited to complet till 31.8.25


Minutes of Meeting Date - 19-Aug-2025

It was commited that V set to be procured for OHT no. 6, 7, 8 & integration will be completed as below ;- OHT nos. 5, 6, 7, 8 till 25.8.25 & OHT no. 3 till 12.8.25. Work not completed and again commited to complet till 31.8.25


Minutes of Meeting Date - 26-Aug-2025

It was commited that V set to be procured for OHT no. 6, 7, 8 & integration will be completed as below ;- OHT nos. 5, 6, 7, 8 till 25.8.25 & OHT no. 3 till 12.8.25. Work not completed and again commited to complet till 31.8.25


Minutes of Meeting Date - 09-Sep-2025

As per commitment OHT no. 6, 7, 8 should have integrated till 31.8.25. V set not receaved at site . Firm again commited to complet remaining OHT till 20.9.25 .


Minutes of Meeting Date - 09-Sep-2025

As per commitment OHT no. 6, 7, 8 should have integrated till 31.8.25. V set not receaved at site . Firm again commited to complet remaining OHT till 20.9.25 .


Minutes of Meeting Date - 16-Sep-2025

It was committed that V set to be procured for OHT no. 6, 7, 8 & integration will be completed as below ;- OHT nos. 5, 6, 7, 8 till 25.8.25 & OHT no. 3 till 12.8.25. Work not completed and again committed to complete till 15.10.25


Minutes of Meeting Date - 23-Sep-2025

It was committed that V set to be procured for OHT no. 6, 7, 8 & integration will be completed as below ;- OHT nos. 5, 6, 7, 8 till 25.8.25 & OHT no. 3 till 12.8.25. Work not completed and again committed to complete till 15.10.25


Minutes of Meeting Date - 07-Oct-2025

It was committed that V set to be procured for OHT no. 6, 7, 8 & integration will be completed as below ;- OHT nos. 5, 6, 7, 8 till 25.8.25 & OHT no. 3 till 12.8.25. Work not completed and again committed to complete till 15.10.25. Work progress is slow and to be expedite .


Minutes of Meeting Date - 21-Oct-2025

It was committed that V set to be procured for OHT no. 6, 7, 8 & integration will be completed as below ;- OHT nos. 5, 6, 7, 8 till 25.8.25 & OHT no. 3 till 12.8.25. Work not completed and again committed to complete till 15.10.25. Work progress is slow and to be expedite .


Minutes of Meeting Date - 28-Oct-2025

V set has been procured for OHT no. 6, 7, 8 . As per Firm recommitment, Integration of OHT nos. 6, 7, 8 should have completed till 15.10.25. Again committed to complete the same till 12.11.25 . Work progress is slow and to be expedite .


Minutes of Meeting Date - 04-Nov-2025

V set has been procured for OHT no. 6, 7, 8 . As per Firm recommitment, Integration of OHT nos. 6, 7, 8 should have completed till 15.10.25. Again committed to complete the same till 12.11.25 . Work progress is slow and to be expedite .


Minutes of Meeting Date - 11-Nov-2025

V set has been procured for OHT no. 6, 7, 8 . As per Firm recommitment, Integration of OHT nos. 6, 7, 8 should have completed till 15.10.25. Again committed to complete the same till 12.11.25 . Work progress is slow and to be expedite . Work progress are same as previous .


Minutes of Meeting Date - 30-Dec-2025

V set has been procured for OHT no. 6, 7 . As per Firm recommitment should have completed till 12.11.25 . Work progress is slow and to be expedite .


Minutes of Meeting Date - 06-Jan-2026

V set has been procured for OHT no. 6, 7 . As per Firm recommitment integration should have completed till 12.11.25 . Firm again committed to complet the same till 16.1.26 .


Minutes of Meeting Date - 13-Jan-2026

V set has been procured for OHT no. 6, 7 . As per Firm recommitment integration should have completed till 12.11.25 . Firm again committed to complet the same till 16.1.26 . Dedicated team not diputed , hence work is still balance .


Minutes of Meeting Date - 20-Jan-2026

V set has been procured for OHT no. 6, 7 . As per Firm recommitment integration should have completed till 12.11.25 . Firm again committed to complet the same till 16.1.26 . Dedicated team not diputed , hence work is still balance .


Minutes of Meeting Date - 27-Jan-2026

As per Firm recommitment integration should have completed till 16.1.26 . All OHT has been made functional now. Dedicated team not diputed , Calibration of instruments & it verification are to be expedite.


Minutes of Meeting Date - 03-Feb-2026

All 8 OHT has been functional . As per Firm recommitment integration should have completed till 16.1.26 . Instruments calibration & it verification to be expedite .