Project Completion Plan


Minutes of Meeting Date - 19-Aug-2025

It was commited that V set to be procured for OHT no. 8, 9 & integration will be completed as below ;- OHT nos. 7, 8 till 20.8.25 & OHT no. 9 till 15.8.25 Work not completed and again commited to complet till 31.8.25


Minutes of Meeting Date - 26-Aug-2025

It was commited that V set to be procured for OHT no. 8, 9 & integration will be completed as below ;- OHT nos. 7, 8 till 20.8.25 & OHT no. 9 till 15.8.25 Work not completed and again commited to complet till 31.8.25


Minutes of Meeting Date - 09-Sep-2025

As per commitment OHT no. 7, 8, 9 should have integrated till 31.8.25. V set not receaved at site . Firm again commited to complet remaining OHT till 20.9.25 .


Minutes of Meeting Date - 16-Sep-2025

As per commitment OHT no. 7, 8, 9 should have integrated till 31.8.25. V set not receaved at site . Firm again commited to make remaining OHT functional till 15.10.25 .


Minutes of Meeting Date - 23-Sep-2025

As per commitment OHT no. 7, 8, 9 should have integrated till 31.8.25. V set not receaved at site . Firm again commited to make remaining OHT functional till 15.10.25 .


Minutes of Meeting Date - 07-Oct-2025

As per commitment OHT no. 7, 8, 9 should have integrated till 31.8.25. V set not receaved at site . Firm again commited to make remaining OHT functional till 15.10.25 . work progress isslow & to be expedite .


Minutes of Meeting Date - 21-Oct-2025

As per commitment OHT no. 7, 8, 9 should have integrated till 31.8.25. V set receaved at site . remaining OHT should have functional till 15.10.25 . work progress isslow & to be expedite . Firm again committed to complet integration till 31.10.25


Minutes of Meeting Date - 28-Oct-2025

As Firm further committment OHT should have functional till 31.10.25 . V set installed at OHT no. 7, 8, 9 now . As per recommitment OHT shall be made functional till 10.11.25 . work progress isslow & to be expedite .


Minutes of Meeting Date - 04-Nov-2025

As Firm further committment OHT should have functional till 31.10.25 . V set installed at OHT no. 7, 8, 9 now . As per recommitment OHT shall be made functional till 10.11.25 . work progress isslow & to be expedite .


Minutes of Meeting Date - 11-Nov-2025

V set installed at OHT no. 7, 8, 9 now . As per recommitment OHT shall be made functional till 10.11.25 . work progress to be expedite .


Minutes of Meeting Date - 30-Dec-2025

V set installed at OHT no. 7, 8, 9 now . As per recommitment OHT shall be made functional till 10.11.25 . work progress to be expedite .


Minutes of Meeting Date - 06-Jan-2026

As per recommitment OHT shall be made functional till 10.11.25 . V set installed at OHT no. 7, 8, 9 but it are to be commissioned . Firm committed again that same shall be completed till 21.1.26.


Minutes of Meeting Date - 13-Jan-2026

As per recommitment OHT shall be made functional till 10.11.25 . V set installed at OHT no. 7, 8, 9 but it are to be commissioned . Firm committed again that same shall be completed till 21.1.26. Dedicated team not diputed , hence work is still balance .


Minutes of Meeting Date - 20-Jan-2026

As per recommitment OHT should have made functional till 10.11.25 . V set installed at OHT no. 7, 8, 9 but it are to be commissioned . Firm committed again that same shall be completed till 21.1.26. Dedicated team not diputed , hence work is still balance .


Minutes of Meeting Date - 27-Jan-2026

As per recommitment integration & it verification should have completed till 21.1.26. 1 OHT has to be functional yet . Calibration of instruments & it verification work to be expedite .


Minutes of Meeting Date - 03-Feb-2026

All OHT has been made functional . Firm committed that calibration & it verification should have completed till 21.1.26. Dedicated team o be deputed .