It was commited that V set to be procured for OHT no. 8, 9 & integration will be completed as below ;- OHT nos. 7, 8 till 20.8.25 & OHT no. 9 till 15.8.25 Work not completed and again commited to complet till 31.8.25
It was commited that V set to be procured for OHT no. 8, 9 & integration will be completed as below ;- OHT nos. 7, 8 till 20.8.25 & OHT no. 9 till 15.8.25 Work not completed and again commited to complet till 31.8.25
As per commitment OHT no. 7, 8, 9 should have integrated till 31.8.25. V set not receaved at site . Firm again commited to complet remaining OHT till 20.9.25 .
As per commitment OHT no. 7, 8, 9 should have integrated till 31.8.25. V set not receaved at site . Firm again commited to make remaining OHT functional till 15.10.25 .
As per commitment OHT no. 7, 8, 9 should have integrated till 31.8.25. V set not receaved at site . Firm again commited to make remaining OHT functional till 15.10.25 .
As per commitment OHT no. 7, 8, 9 should have integrated till 31.8.25. V set not receaved at site . Firm again commited to make remaining OHT functional till 15.10.25 . work progress isslow & to be expedite .
As per commitment OHT no. 7, 8, 9 should have integrated till 31.8.25. V set receaved at site . remaining OHT should have functional till 15.10.25 . work progress isslow & to be expedite . Firm again committed to complet integration till 31.10.25
As Firm further committment OHT should have functional till 31.10.25 . V set installed at OHT no. 7, 8, 9 now . As per recommitment OHT shall be made functional till 10.11.25 . work progress isslow & to be expedite .
As Firm further committment OHT should have functional till 31.10.25 . V set installed at OHT no. 7, 8, 9 now . As per recommitment OHT shall be made functional till 10.11.25 . work progress isslow & to be expedite .
V set installed at OHT no. 7, 8, 9 now . As per recommitment OHT shall be made functional till 10.11.25 . work progress to be expedite .
V set installed at OHT no. 7, 8, 9 now . As per recommitment OHT shall be made functional till 10.11.25 . work progress to be expedite .
As per recommitment OHT shall be made functional till 10.11.25 . V set installed at OHT no. 7, 8, 9 but it are to be commissioned . Firm committed again that same shall be completed till 21.1.26.
As per recommitment OHT shall be made functional till 10.11.25 . V set installed at OHT no. 7, 8, 9 but it are to be commissioned . Firm committed again that same shall be completed till 21.1.26. Dedicated team not diputed , hence work is still balance .
As per recommitment OHT should have made functional till 10.11.25 . V set installed at OHT no. 7, 8, 9 but it are to be commissioned . Firm committed again that same shall be completed till 21.1.26. Dedicated team not diputed , hence work is still balance .
As per recommitment integration & it verification should have completed till 21.1.26. 1 OHT has to be functional yet . Calibration of instruments & it verification work to be expedite .
All OHT has been made functional . Firm committed that calibration & it verification should have completed till 21.1.26. Dedicated team o be deputed .