It was commited that V set to be procured for OHT no. 8, 9 & integration will be completed as below ;- OHT nos. 7, 8 till 20.8.25 & OHT no. 9 till 15.8.25 Work not completed and again commited to complet till 31.8.25
It was commited that V set to be procured for OHT no. 8, 9 & integration will be completed as below ;- OHT nos. 7, 8 till 20.8.25 & OHT no. 9 till 15.8.25 Work not completed and again commited to complet till 31.8.25
As per commitment OHT no. 7, 8, 9 should have integrated till 31.8.25. V set not receaved at site . Firm again commited to complet remaining OHT till 20.9.25 .
As per commitment OHT no. 7, 8, 9 should have integrated till 31.8.25. V set not receaved at site . Firm again commited to make remaining OHT functional till 15.10.25 .
As per commitment OHT no. 7, 8, 9 should have integrated till 31.8.25. V set not receaved at site . Firm again commited to make remaining OHT functional till 15.10.25 .
As per commitment OHT no. 7, 8, 9 should have integrated till 31.8.25. V set not receaved at site . Firm again commited to make remaining OHT functional till 15.10.25 . work progress isslow & to be expedite .